Marine Turbocharger Overhaul DNV & Lloyd's Register Certified Completed & In Service

Marine Vessel Turbocharger Overhaul & High-Speed Dynamic Balancing

Complete turbocharger refit, ultrasonic cleaning, and rotor balancing for 85,000 DWT Container Carrier

Engineering Documentation Video
Watch on YouTube
Project ID: MARINEV-2024 • Location: Chittagong Port & Outer Anchorage
Client: Pacific Oceanic Shipping Lines Ltd.

Project Overview & Operational Context

During an international transit call, the 85,000 DWT container vessel experienced severe exhaust turbine vibrations exceeding 14.2 mm/s RMS, requiring immediate emergency intervention before onward ocean passage. Nordroy Marine dispatched an emergency response squad aboard with complete diagnostic instruments and genuine OEM spare kits.

Engineering Performance Metrics

97.2%

Vibration Reduction

Reduced from 14.2 mm/s to 0.4 mm/s

32 Hours

Port Turnaround

Delivered 4 hours ahead of vessel sailing schedule

$130,000+

Cost Savings

Demurrage averted & fuel efficiency restored

12 Months

Warranty Coverage

Comprehensive marine class warranty

The Engineering Challenge

The ship had only a strict 36-hour berth window before scheduled departure. Failure to balance the rotor within this window would result in severe port demurrage penalties ($65,000/day) and risk complete catastrophic turbine blade rupture on high seas.

Engineered Remediation

Our team extracted the turbocharger cartridge on-site, transported it to our certified workshop, performed ultrasonic chemical decarbonization, replaced worn labyrinth seals and ceramic journal bearings, and completed dynamic rotor balancing on our calibrated Schenck balance bench down to ISO 1940 Grade G1.0 tolerance (0.42 mm/s residual vibration). The cartridge was re-installed and validated during full sea-trial engine loading.

Scope of Technical Work & Overhaul Steps

  • Complete cartridge extraction and heavy rigging operations aboard ship
  • Ultrasonic chemical decarbonization of turbine blades and compressor wheel
  • Precision rotor shaft micro-TIG re-profiling and run-out inspection
  • High-speed dynamic balancing conforming to ISO 1940 Grade G1.0
  • Replacement of thrust bearings, journal bearings, and oil seals with OEM parts
  • Static pressure testing of water-cooled turbine casing at 4.5 bar
  • Re-installation, torque-angle bolt tightening, and sea-trial data logging

Photographic Documentation

Click photo to enlarge
Project Photo 1
View Photo →
Project Photo 2
View Photo →
Project Photo 3
View Photo →
Project Photo 4
View Photo →

Project Specifications

2024
Client
Pacific Oceanic Shipping Lines Ltd.
Location / Port
Chittagong Port & Outer Anchorage
Industry Sector
Commercial Shipping & Maritime Freight
Equipment Rating
MAN NR/S 34 Series (18,500 Max RPM)
Execution Window
36 Hours Turnaround (Zero Port Demurrage)
Classification
DNV & Lloyd's Register Certified
Project Status
Completed & In Service
24/7 Port Call Squad

Need Urgent Flying Squad or Dynamic Balancing?

Our mobile engineering squads mobilize within 2-4 hours for maritime anchorage and industrial plants across Bangladesh and Southeast Asia.

Portfolio

Other Featured Case Studies

View All Projects →
2.5MW Industrial Power Plant Turbocharger Refit & Overhaul
Industrial Captive Power

2.5MW Industrial Power Plant Turbocharger Refit & Overhaul

Continuous heavy-duty turbine overhaul and compressor cartridge overhaul for heavy manufacturing plant

Gazipur Industrial Belt, Bangladesh View Case Study →
Emergency Anchorage Flying Squad Turbocharger Cartridge Swap
Emergency Flying Squad

Emergency Anchorage Flying Squad Turbocharger Cartridge Swap

Rapid boarding at outer anchorage via offshore tug to replace wrecked turbocharger cartridge at sea

Outer Anchorage (Deep Sea Anchorage, Bay of Bengal) View Case Study →